Temporary Road Closure-Faringdon, Market Place

Notice of Temporary Traffic Order

Location: Faringdon, Market Place

Date of Order: 14 June 2021

Coming into force: 22 June 2021

This Order is being introduced because of restoration work to the town hall which is anticipated to be completed on 1 August 2021.

The effect of the Order is to temporarily prohibit any vehicle proceeding in the whole length of the Market Place

Appropriate traffic signs will be displayed to indicate when the measures are in force.

Exemptions are included for police, fire and ambulance services and for the works and for access to premises which are only accessible from the closed section of road.

The alternative route for traffic affected by the closure is via A4095 – Marlborough Street- vice versa.

The alternative route for traffic is to the south of Market Place.

Temporary Road Closure – Faringdon, Market Place

LOCATION:  Faringdon, Market Place

REASON: To facilitate carriageway resurfacing, relining and remarking

DURATION: Starting on  28 October 2021 at 20:00    

The anticipated completion date is 29 October 2021 at 06:00 (date included)

(Traffic Regulation Notices cover a maximum of 5 consecutive days.)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

The “No Waiting” restriction means that wherever there are in place yellow “No Waiting” cones, you will not be able to park vehicles on the highway.

SUGGESTED ALTERNATIVE ROUTE: Through traffic using the A4095 will be diverted back north along the A4095 through Clanfield to Bampton, to turn east onto the B4449 High Street following it around into Buckland Road heading south, to cross the River Thames and down to Buckland, to turn back west along the A420, to turn into Faringdon using the A4095 London Street returning back to Market Place, and vice versa

Temporary Road Closure – Faringdon, Park Road and Station Road

Notice of Temporary Traffic Order

LOCATION: Faringdon – Park Road and Station Road

DURATION: Date of Order: 02 August 2021 .Coming into force: 09 August 2021.This Order is being introduced because of carriageway resurfacing works which are anticipated to be completed 21 August 2021. This will operate between 20:00 and 06:00hrs.

The effect of the Order is to temporarily prohibit any vehicle proceeding in Park Road and Station Road to its junction with the B4019.

Appropriate traffic signs will be displayed to indicate when the measures are in force.

Exemptions are included for emergency services and for the works and for access to premises which are only accessible from the closed section of road. The alternative route for traffic is via the B4019, A420 and vice versa

For more details see below:

TEMPORARY ROAD CLOSURE-WHITE HART JUNCTION IMPROVEMENTS

New Eastern Villages – White Hart Junction Improvement


We are mid-way through the programme for carriageway works and thank you for your ongoing support of this project.


LOCATION: Please be aware that we will be carrying out kerb and drainage works to the junction of Wanborough Road and Oxford Road, along with the new section of Ermin Street (see attached drawing).

DURATION: This work will take place from 22 March to 9 April, on weekdays between 7.30am and 5.30pm.


During this time, the junction will be fully closed and access between Oxford Road and Wanborough Road will be diverted via the White Hart Roundabout and Merlin Way.

Traffic along Oxford Road will be managed with a contraflow for the safety of road users and workers. In addition, a temporary pedestrian diversion will be in place around the works area.


We apologise for any disturbance or inconvenience you may experience due to this work

Temporary Road Closure: Gablecross lane

Works on the westbound carriageway of the A420 in conjunction with the Gablecross Improvements Scheme.

The programmed work will be to construct a new section of footway from Symmetry park to Gablecross roundabout. As works are in the channel of the carriageway a lane closure of the westbound A240 is required to undertake the works safely.


To safely control traffic past the junction of the A420 with the Police access road; temporary traffic lights will replace the existing 3-way signalised junction.
Start :on the A420 on the 22nd of February for a eight-week duration.

The lane closure will be in place from 09:30 hours to 15:30 hours, but the temporary traffic lights will remain on site for the duration of this work.

WHITE HART JUNCTION IMPROVEMENTS – EMERGENCY WORKS –

Please note that we will be carrying out emergency pothole repairs to the north east section of the White Hart Roundabout, between the A419 southbound exit and A420 westbound entry slips.

This section of the roundabout will be closed from 10pm Thursday 4 February while this work takes place. We anticipate the repairs to take around three hours before the roundabout will be re-opened.

Temporary Road Closure: Bradwell Grove, A361

ROAD TRAFFIC REGULATION ACT, 1984

TEMPORARILY PROHIBITS THE USE OF AND WAITING ON THE HIGHWAY

BY ALL MOTOR VEHICLES

LOCATION:  Bradwell Grove, A361

REASON: To facilitate carriageway patching works

DURATION: Starting on 08 April 2021

The anticipated completion date is 13 April 2021 (date included). This will operate between 05:00 to 7:30, 09:30 to15:30 and 18:00 to 20:00

(Traffic Regulation Notices cover a maximum of 5 consecutive days.)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

The “No Waiting” restriction means that wherever there are in place yellow “No Waiting” cones, you will not be able to park vehicles on the highway.

SUGGESTED ALTERNATIVE ROUTE: via A361, A417, A429, A40, A361 and vice versa

Site 14 – A361 Bradwell Grove

Site 14 – A361 Bradwell Grove

Temporary Road closure – Faringdon, Church Street

Notice is hereby given pursuant to Section 14(2) of the Road Traffic Regulation Act, 1984, that the Oxfordshire County Council

TEMPORARY ONE-WAY RESTRICTION

(Two-way traffic to One-way)

LOCATION: Faringdon, Church Street  (26 to 34 Church Street)  

REASON: To facilitate excavation across the road and electrical installation for new customer

DURATION: Starting on 18 January 2021

The anticipated completion date is 22 January 2021.

This is a 24 hour two way to one way. (Traffic Regulation Notices cover a maximum of 5 consecutive days)

To see the plan and the suggested alternative route open the link below:


Temporary Road Closure -Faringdon, Sand Hill

TEMPORARILY PROHIBITS THE USE OF THE HIGHWAY BY ALL MOTOR VEHICLES

LOCATION: Faringdon, Sand Hill

REASON: Excavate carriageway

DURATION: Starting on 10 February 2021

The anticipated completion date is 12 February 2021

(full closure 24 hours each day)

(Traffic Regulation Notices cover a maximum of 5 consecutive days)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

SUGGESTED ALTERNATIVE ROUTE: There will be no alternative routes for traffic the road is cul-de-sac.

Please click on the link below to read more about this road closure :

Buckland & Pusey, A420 (between B4508 and Buckland Road)

TRAFFIC REGULATION NOTICE

ROAD TRAFFIC REGULATION ACT, 1984

 Notice is hereby given pursuant to Section 14(2) of the Road Traffic Regulation Act, 1984, that the Oxfordshire County Council

TEMPORARILY PROHIBITS THE USE OF THE HIGHWAY

BY ALL MOTOR VEHICLES

         LOCATION:         Buckland & Pusey, A420 (between B4508 and Buckland Road)

         REASON:           Serious incident and subsequent road repairs in the

                                      interests of safety of all users.

         DURATION:         Started on 16 July 2020 (at 04:00hrs)

                                     The anticipated completion date is 17 July 2020 (at 06:00hrs)

                                      (date included)  (full closure 24hrs each day)

                                      (Emergency Traffic Regulation Notices cover a  maximum of 21 days)

         ACCESS:             Will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

         SUGGESTED ALTERNATIVE ROUTE:  The alternative routes for traffic

         are via a combination of  A417 – A338 – A415 and vice-versa.

         Jason Russell, Director for Infrastructure Delivery

Communities                                                                    Date: 16 July 2020