White Hart junction roundabout reconstruction

Major reconstruction work will start at White Hart roundabout on 16 August 2021 to increase the life expectancy of the road.

The additional work, which is expected to last an estimated 12 weeks, will involve digging down almost a metre beneath the surface to build a new structure for the road base.

The nature of the work means it will not be safe to keep the roundabout open to through traffic. Access will be maintained for emergency services only and diversions will be in place for all other road users.

We anticipate motorists will be able to use the new roundabout by November 2021. 

Traffic will still be able to use the junction to leave the A419 southbound to join the A420 eastbound, or to leave the A420 westbound to join the A419 southbound only. A map of the diversionary route can be viewed below:

Temporary Road Closure, Faringdon-Carriageway Maintenance

I am writing to inform you that Oxfordshire County Council will be undertaking carriageway
maintenance work on Park Road between the A420 roundabout and Marlborough Street.
The works are programmed to start on Monday 2nd August 2021 and are expected to last for up to 3 weeks, subject to any bad weather conditions or unforeseen circumstances arising during construction.
The works will include replacing damaged road signs, traffic bollards and ironwork, resurfacing of the existing carriageway and the replacement of road markings.


Traffic Management

To enable these activities to be carried out safely the work will be done in the following phases:


Phase 1: Monday 2nd August to Wednesday 4th August, 20:00 to 06:00hrs – temporary
traffic signals to enable preparation work to be carried out, including replacing damaged
road signs, traffic bollards and ironwork.


Phase 2: Monday 9th August to Friday 20th August, 20:00 to 06:00hrs – full road closure
to enable the resurfacing work to be carried out and replacement of road markings. A
signed diversion route will be put in place during this period.

Park Road will be reopened to traffic when safe to do so outside of these periods.
Staff will be positioned at either end of the closure to direct traffic and pedestrians to ensure the safety of the public and workforce.

We ask that you give them your full support whether you are a pedestrian, cyclist, or motorist.
Every effort will be made to accommodate vehicular access to properties and businesses within and adjacent to the works, but this may be subject to some delay depending on the activities being carried out on site.

Again, I ask for your support during these periods.

We have consulted with Vale of White Horse District Council’s Environmental department
regarding carrying out these works at night. As part of this consultation the noisier operations,
i.e. removing the existing carriageway and breaking out, will cease by 11pm. Unfortunately, the remaining operations are not completely silent, but the site team will be briefed to complete the work with as little disruption and as quietly as practicably possible.

Keeping You Informed

Several methods of communication are being used to keep you informed of these works:
Signs are being placed on site to forewarn road users in advance of the works. A maintenance information website, which will be updated should any changes occur:
www.oxfordshire.gov.uk/residents/roads-and-transport/roadworks/road-maintenanceinformation

We apologise in advance for any inconvenience caused. However, we will do our utmost to
complete this work as safely and as quickly as possible.


Yours faithfully,
Andrew Madigan
Principal Engineer – Structural Maintenance
Environment & Place

Temporary Road Closure, Bampton, Buckland Road

TEMPORARILY PROHIBITS THE USE OF THE HIGHWAY BY ALL MOTOR VEHICLES

LOCATION: Bampton , Buckland Road

REASON: To facilitate repairs to a damaged bridge parapet

DURATION: Starting on 12 September 2021
The anticipated completion date is 17 September 2021 (date included). Closure will operate brightly between 22:00 and 05:00 .
(Traffic Regulation Notices cover a maximum of 5 consecutive days.)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

SUGGESTED ALTERNATIVE ROUTE: via B4449 > A4095 > London Street,
Farringdon > A420 and vice versa

Temporary Road Closure, Faringdon, Market Place

Notice of Temporary Traffic Order

Location: Faringdon, Market Place

Prohibition of Through Traffic

This Order is being introduced because of restoration work to the town hall which is anticipated to be completed on 30 August 2021.

The effect of the Order is to temporarily prohibit any vehicle proceeding in the whole length of the Market Place.

Appropriate traffic signs will be displayed to indicate when the measures are in force.

Exemptions are included for police, fire and ambulance services and for the works and for access to premises which are only accessible from the closed section of road.

Alternative route: A4095 – via Marlborough Street- vice versa

The alternative route for traffic is to the south of Market Place.

Temporary Road Closure-Faringdon, 11 Pulling Close

TRAFFIC REGULATION NOTICE

Notice is hereby given pursuant to Section 14(2) of the Road Traffic Regulation Act, 1984, that the Oxfordshire County Council

TEMPORARILY PROHIBITS THE USE OF THE HIGHWAY

BY ALL MOTOR VEHICLES

LOCATION: Faringdon, 11 Pulling Close

REASON:   To facilitate BT Openreach Fibre Cabling Works

DURATION:  Starting on  6 September 2021

The anticipated completion date is 8 September 2021

(full closure 24hrs each day)

(Traffic Regulation Notices cover a maximum of 5 consecutive days.)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

SUGGESTED ALTERNATIVE ROUTE: There is no alternative routes for traffic as this road is a dead end.

Temporary Road Closure-Faringdon, Market Place

Notice of Temporary Traffic Order

Location: Faringdon, Market Place

Date of Order: 14 June 2021

Coming into force: 22 June 2021

This Order is being introduced because of restoration work to the town hall which is anticipated to be completed on 1 August 2021.

The effect of the Order is to temporarily prohibit any vehicle proceeding in the whole length of the Market Place

Appropriate traffic signs will be displayed to indicate when the measures are in force.

Exemptions are included for police, fire and ambulance services and for the works and for access to premises which are only accessible from the closed section of road.

The alternative route for traffic affected by the closure is via A4095 – Marlborough Street- vice versa.

The alternative route for traffic is to the south of Market Place.

Temporary Road Closure – Faringdon, Market Place

LOCATION:  Faringdon, Market Place

REASON: To facilitate carriageway resurfacing, relining and remarking

DURATION: Starting on  28 October 2021 at 20:00    

The anticipated completion date is 29 October 2021 at 06:00 (date included)

(Traffic Regulation Notices cover a maximum of 5 consecutive days.)

ACCESS: Limited access will be maintained for emergency service vehicles and for frontages within the closed section of road, subject to the progress of the works

The “No Waiting” restriction means that wherever there are in place yellow “No Waiting” cones, you will not be able to park vehicles on the highway.

SUGGESTED ALTERNATIVE ROUTE: Through traffic using the A4095 will be diverted back north along the A4095 through Clanfield to Bampton, to turn east onto the B4449 High Street following it around into Buckland Road heading south, to cross the River Thames and down to Buckland, to turn back west along the A420, to turn into Faringdon using the A4095 London Street returning back to Market Place, and vice versa

Temporary Road Closure – Faringdon, Park Road and Station Road

Notice of Temporary Traffic Order

LOCATION: Faringdon – Park Road and Station Road

DURATION: Date of Order: 02 August 2021 .Coming into force: 09 August 2021.This Order is being introduced because of carriageway resurfacing works which are anticipated to be completed 21 August 2021. This will operate between 20:00 and 06:00hrs.

The effect of the Order is to temporarily prohibit any vehicle proceeding in Park Road and Station Road to its junction with the B4019.

Appropriate traffic signs will be displayed to indicate when the measures are in force.

Exemptions are included for emergency services and for the works and for access to premises which are only accessible from the closed section of road. The alternative route for traffic is via the B4019, A420 and vice versa

For more details see below:

TEMPORARY ROAD CLOSURE-WHITE HART JUNCTION IMPROVEMENTS

New Eastern Villages – White Hart Junction Improvement


We are mid-way through the programme for carriageway works and thank you for your ongoing support of this project.


LOCATION: Please be aware that we will be carrying out kerb and drainage works to the junction of Wanborough Road and Oxford Road, along with the new section of Ermin Street (see attached drawing).

DURATION: This work will take place from 22 March to 9 April, on weekdays between 7.30am and 5.30pm.


During this time, the junction will be fully closed and access between Oxford Road and Wanborough Road will be diverted via the White Hart Roundabout and Merlin Way.

Traffic along Oxford Road will be managed with a contraflow for the safety of road users and workers. In addition, a temporary pedestrian diversion will be in place around the works area.


We apologise for any disturbance or inconvenience you may experience due to this work

Temporary Road Closure: Gablecross lane

Works on the westbound carriageway of the A420 in conjunction with the Gablecross Improvements Scheme.

The programmed work will be to construct a new section of footway from Symmetry park to Gablecross roundabout. As works are in the channel of the carriageway a lane closure of the westbound A240 is required to undertake the works safely.


To safely control traffic past the junction of the A420 with the Police access road; temporary traffic lights will replace the existing 3-way signalised junction.
Start :on the A420 on the 22nd of February for a eight-week duration.